A game of inches
Met with the excavator yesterday at the site. We talked about window placement, and decided to not bother with windows on the south side since we are building a deck there eventually. Also some confusion on the actual width of the foundation, allowing for a 2”foam insulation on the outside. He is used to shrinking the foundation 4” to allow for the extra 2” all around. This seemed to make sense, but the closer we looked at the plans, the more it seemed he needed to do a full pour. We called J. at first day and left a message and hopefully will hear from him. At any rate, we need to figure this out before Monday.
Why Monday? Because they are coming to pour the footings on Monday. Then the walls Tuesday. Then they prep the floor for a pour, and we install the radiant heat over the weekend (which is Labor Day weekend, so we get an extra day to finish). Then they pour the floor next Tuesday (5th), and the house arrives Thursday. All in all, full speed ahead.
richard